Lincoln authorizes up to $100,000 for ledge blasting at community center site Lincoln's community center project hit ledge, and the building committee approved blasting to remove it.
Lincoln Panel Rejects $1,331 Partition Credit, OKs $30,000 Bridge Fix Lincoln building panel rejects contractor's partition credit, presses ahead on $30,000 bridge fix.
Lincoln panel approves $323,000 in community center cost increases Lincoln Community Center Building Committee approves $323,000 in cost increases as project runs four months late.
Committee authorizes site regrade, approves $456,000 in furnishings Lincoln community center committee unanimously authorizes $456,000 in furniture and appliance contracts. Co-chairs Jonathan Dwyer and Sarah Chester led approval of procurement contracts not to exceed $267,000 for furniture and $189,000 for kitchen appliances, with $77,806 allocated from contingency
Community Center Building Committee approves solar panel coordination changes Lincoln Community Center Building Committee approves solar coordination changes. The committee voted unanimously to authorize $6,434 for roof vent piping relocation and approved 5-1-2 a $12,675 structural roof reinforcement, both required to coordinate the solar panel vendor's installation plan